Date of meeting: 26 Jan 2012
Time of meeting: 1030hours
Venue of meeting: SIM e-learning
Absentee: NIL
Agenda of meeting
1. Complete the required sections in the proposal; Roles, Risk management, Objectives, Scope and problems of limitations, Literature Review, Project Introduction and Executive Summary
2. Discuss and get these components done as a team together
Discussion content
1. Overall of program to be confirmed by Dr Loo the next meeting
2. Scope of program to be confirmed by Dr Loo the next meeting
Work to be done:
[Due on 29th]
1. Timetable (Gantt Chart) update to be done by Rudy.
2. Risk management and development process update to be done by Xiao Wei.
3. Prototype GUI to be done by Shanlong.
4. Tool & Software and Goals & expected outcomes to be done by Bryan.
No comments: